Inspection Status: Partial Pass

Inspection History: COT - HCME - Mechanical Above Ceiling

Date Description Inspector Results Comments
06/25/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 6/25/25: partial pass ok to proceed with grid ceiling
07/16/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 7-16-25: mechanical above ceiling for serving area, kitchen, IT room #103, break room #102, and vault room. Okay to continue with construction at progress areas.
08/14/2025 COT - HCME - Mechanical Above Ceiling Partial Pass 8-14-25: partial pass pending RFI on 3-Variable Air Volume(VAV) terminal units set future installation in room's 102, 103, & 104. Okay to continue with construction at progress areas.
08/28/2025 COT - HCME - Mechanical Above Ceiling Passed