Inspection Status: Partial Pass
Inspection History: COT - HCME - Mechanical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 06/25/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
6/25/25: partial pass ok to proceed with grid ceiling |
| 07/16/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
7-16-25: mechanical above ceiling for serving area, kitchen, IT room #103, break room #102, and vault room. Okay to continue with construction at progress areas. |
| 08/14/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
8-14-25: partial pass pending RFI on 3-Variable Air Volume(VAV) terminal units set future installation in room's 102, 103, & 104. Okay to continue with construction at progress areas. |
| 08/28/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Passed |
|