Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Progress  

Date Description Inspector Results Comments
08/13/2025 COT - HCEL - Electrical Progress   Partial Pass 8-13-25: verified grounding/bonding of XFRM -DP2 & PNL-DP2, conduit supports & labelling of junction boxes above ceiling.
Pending labelling of all in wall junction boxes at storage area.
08/22/2025 COT - HCEL - Electrical Progress   Partial Pass 8-22-25: complete wiring on panic hardware fire exit signs, install receptacle covers at janitor room, label all junction boxes at back storage areas and at water heater room.
08/28/2025 COT - HCEL - Electrical Progress   Passed