Inspection Status: Re-inspection required
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 02/03/2025 |
ENGR Engineering Final
|
|
Re-inspection required |
Not ready for an inspection at this time, all construction needs to be completed. Dumpster removed, Conex removed, Port-A-Jons removed and all construction materials need to be removed. |
| 02/06/2025 |
ENGR Engineering Final
|
|
Passed |
Everything is completed, please re-rake the DG on the side of the store where tile was being cut. |