| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/30/2024 | COT - HCEL - Grounding/Bonding | Not Ready | ||
| 06/04/2024 | COT - HCEL - Grounding/Bonding | Partial Pass | ||
| 07/09/2024 | COT - HCEL - Grounding/Bonding | Partial Pass | Partial approval for SCS under slab 7/9/24: grounding at 7 light pole bases per plan ok to proceed, |
|
| 09/16/2024 | COT - HCEL - Grounding/Bonding | Not Ready | 9/16/24 please ground electrical boxes, brace and clamp roof drains, complete continuous plate at required areas, fire stop top plates... | |
| 11/08/2024 | COT - HCEL - Grounding/Bonding | Partial Pass | ||
| 11/13/2024 | COT - HCEL - Grounding/Bonding | Passed |