| 07/02/2024 | COT - HCEL - Electrical Progress | Partial Pass | ||
| 07/03/2024 | COT - HCEL - Electrical Progress | Not Ready | ||
| 07/09/2024 | COT - HCEL - Electrical Progress | Partial Pass | Partial approval for 4 inch conduit four secondary power, minus sweeps at building and at pole or transformer, ok to cover 7/9/24: (2)4" conduit from primary to transformer ok to backfill.(2)4" conduit for secondary's at transformer ok to backfill, 7 light pole bases per plan ok to proceed. |
|
| 09/16/2024 | COT - HCEL - Electrical Progress | Re-inspection required | 9/16/24 please ground electrical boxes, brace and clamp roof drains, complete continuous plate at required areas, fire stop top plates... | |
| 09/17/2024 | COT - HCEL - Electrical Progress | Partial Pass | ok to insulate | |
| 11/08/2024 | COT - HCEL - Electrical Progress | Passed |