Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - CofO
Permit Number - TC-COM-1223-02911
Inspection Description - COT - HCBU - CofO
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/08/2025 | COT - HCBU - CofO | Not Ready | ||
| 08/22/2025 | COT - HCBU - CofO | Re-inspection required | ||
| 09/05/2025 | COT - HCBU - CofO | Re-inspection required | 9/5/25: Air gaps required throughout at discharge of condensation in bathroom, filtration system, leak at ice maker, hunter low voltage box on east side of cooler must be properly secured, plastic piping on exterior of building must be coated for UV protection, secure schedule 40 pvc in hunter box and properly terminate in box with approved fitting. leak at filtration system.Water sterilization report has not been approved. Pending engineering final. | |
| 09/24/2025 | COT - HCBU - CofO | Partial Pass | 9/24/25: leak at water filtration system, exterior lighting must be on timer and must turn off after business hours, irrigation must be tested during inspection. Pending conditions. Okay for level 2 TCO | |
| 10/03/2025 | COT - HCBU - CofO | Partial Pass | 10/3/25: OKAY FOR LEVEL 4 TCO | |
| 10/02/2025 | COT - HCBU - CofO | Re-inspection required | 10/2/25: Leak at water filtration system, GFCI receptacle trips when in use at water filtration system. Air gap required at coffee equipment discharge, exterior camera/light that was removed must be replaced or cap the penetrations at north east corner. | |
| COT - HCBU - CofO | Scheduled |