Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Framing
Permit Number - TC-COM-1222-00269
Inspection Description - COT - HCBU - Framing
Inspection Status - Re-inspection required
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2025 | COT - HCBU - Framing | Re-inspection required | No access for inspection. | |
| 05/30/2025 | COT - HCBU - Framing | Not Ready | Met with workman. This was not an intermediate; consultation only. Wood only details need 5/8" bolts installed. Masonry has not been completed per plan. | |
| 06/23/2025 | COT - HCBU - Framing | Re-inspection required | 6-23-25: provide truss calculations for unit d. Reschedule framing/roof/sheathing inspection.when ready. | |
| 06/25/2025 | COT - HCBU - Framing | Re-inspection required | 6-25-25: pending revision corrections. For questions regarding plan review comments contact: Dino M. Accardo, MCP,CBO,E. Email daccardo@willdan.com | |
| 06/27/2025 | COT - HCBU - Framing | Re-inspection required | 6-27-25: Unit D1-4, missing bathroom backing for future grabars on each unit, install tap con anchors at 16" o.c. for wall fur out sill plates and on interior load bearing walls 1/2 anchor bolts are required at 16" o.c. And where there is splice on the sill plate, an anchor is required 12" o.c. on each side, finish framing at doors and at windows-see plans for details, add backing/sheathing per fire rated wall detail, missing bracing at 2 areas for truss A01, okay to dry in roof but a ladder is required to check sheathing at parapets-do not cover sheathing at parapets. | |
| 08/01/2025 | COT - HCBU - Framing | Partial Pass | 12-3-24: Work is continuing that is not shown on approved plans. No access for inspection. Met with workman. This was not an intermediate; consultation only. Wood only details need 5/8" bolts installed. Masonry has not been completed per plan. 6-23-25: provide truss calculations for unit d. Reschedule framing/roof/sheathing inspection.when ready. 6-25-25: pending revision corrections. For questions regarding plan review comments contact: Dino M. Accardo, MCP,CBO,E. Email daccardo@willdan.com. 6-27-25: Unit D1-4, missing bathroom backing for future grabars on each unit, install tap con anchors at 16" o.c. for wall fur out sill plates and on interior load bearing walls 1/2 anchor bolts are required at 16" o.c. And where there is splice on the sill plate, an anchor is required 12" o.c. on each side, finish framing at doors and at windows-see plans for details, add backing/sheathing per fire rated wall detail, missing bracing at 2 areas for truss A01, okay to dry in roof but a ladder is required to check sheathing at parapets-do not cover sheathing at parapets. 8/1/25: Ok to one-side partition walls. |
|
| 09/03/2025 | COT - HCBU - Framing | Passed | ||
| 12/03/2024 | COT - HCBU - Framing | Not Ready | 12-3-24: Work is continuing that is not shown on approved plans. |