Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-1222-00264
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/04/2025 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. 4/4/25: steel decking at the roof of the classrooms passed ok to proceed |
|
| 04/16/2025 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. 4/4/25: steel decking at the roof of the classrooms passed ok to proceed 4/16/25: framing approved at pre-rock at drop ceiling areas |
|
| 04/18/2025 | COT - HCBU - Building Progress | Partial Pass | 4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas. | |
| 04/21/2025 | COT - HCBU - Building Progress | Canceled | ||
| 04/22/2025 | COT - HCBU - Building Progress | Partial Pass | 4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas. | |
| 04/29/2025 | COT - HCBU - Building Progress | Partial Pass | 4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom. | |
| 05/01/2025 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. 4/4/25: steel decking at the roof of the classrooms passed ok to proceed 4/16/25: framing approved at pre-rock at drop ceiling areas 4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas. 4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas. 4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom. 5/1/25: Inspection for insulation at the classrooms in wall |
|
| 05/08/2025 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. 4/4/25: steel decking at the roof of the classrooms passed ok to proceed 4/16/25: framing approved at pre-rock at drop ceiling areas 4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas. 4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas. 4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom. 5/1/25: Inspection for insulation at the classrooms in wall 5/8/25: drywall nailing passed, |
|
| 05/09/2025 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. 4/4/25: steel decking at the roof of the classrooms passed ok to proceed 4/16/25: framing approved at pre-rock at drop ceiling areas 4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas. 4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas. 4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom. 5/1/25: Inspection for insulation at the classrooms in wall 5/8/25: drywall nailing passed |
|
| 05/13/2025 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. 4/4/25: steel decking at the roof of the classrooms passed ok to proceed 4/16/25: framing approved at pre-rock at drop ceiling areas 4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas. 4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas. 4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom. 5/1/25: Inspection for insulation at the classrooms in wall 5/8/25: drywall nailing passed, 5/13/25: drywall nailing at breezeway passed. Ok to proceed |
|
| 07/25/2025 | COT - HCBU - Building Progress | Passed | 7-25-25: approved | |
| 11/19/2024 | COT - HCBU - Building Progress | Partial Pass | 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings. |