Parcel: 30503004B


Addresses:

10001 S WILMOT RD


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Permit Number - TC-COM-1222-00264

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/04/2025 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
4/4/25: steel decking at the roof of the classrooms passed ok to proceed
04/16/2025 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
4/4/25: steel decking at the roof of the classrooms passed ok to proceed
4/16/25: framing approved at pre-rock at drop ceiling areas
04/18/2025 COT - HCBU - Building Progress Partial Pass 4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas.
04/21/2025 COT - HCBU - Building Progress Canceled
04/22/2025 COT - HCBU - Building Progress Partial Pass 4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas.
04/29/2025 COT - HCBU - Building Progress Partial Pass 4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom.
05/01/2025 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
4/4/25: steel decking at the roof of the classrooms passed ok to proceed
4/16/25: framing approved at pre-rock at drop ceiling areas
4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas.

4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas.
4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom.
5/1/25: Inspection for insulation at the classrooms in wall
05/08/2025 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
4/4/25: steel decking at the roof of the classrooms passed ok to proceed
4/16/25: framing approved at pre-rock at drop ceiling areas
4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas.

4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas.
4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom.
5/1/25: Inspection for insulation at the classrooms in wall
5/8/25: drywall nailing passed,
05/09/2025 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
4/4/25: steel decking at the roof of the classrooms passed ok to proceed
4/16/25: framing approved at pre-rock at drop ceiling areas
4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas.

4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas.
4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom.
5/1/25: Inspection for insulation at the classrooms in wall
5/8/25: drywall nailing passed
05/13/2025 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
4/4/25: steel decking at the roof of the classrooms passed ok to proceed
4/16/25: framing approved at pre-rock at drop ceiling areas
4-18-25, nailing/framing for mock up pitch roof framing at shooting deck is okay to shingle, crickets at virtual classrooms roof decking is per plan, and verified framing/washer/bolts between virtual classrooms (steal decking not installed-inspection required). Okay to continue with construction at progress areas.

4-22-25, nailing/screws for roof decking between virtual classroom's breezeway approved. Okay to continue with construction at progress areas.
4-29-25, in wall plumbing/electrical at virtual classrooms verified under test. Okay to continue with construction at progress areas. Provide 15 pound gauge to test 20 ft. Of gas line from meter to virtual classroom.
5/1/25: Inspection for insulation at the classrooms in wall
5/8/25: drywall nailing passed,
5/13/25: drywall nailing at breezeway passed. Ok to proceed
07/25/2025 COT - HCBU - Building Progress Passed 7-25-25: approved
11/19/2024 COT - HCBU - Building Progress Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.