Parcel: 30503004B


Addresses:

10001 S WILMOT RD


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-1222-00264

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/02/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
01/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
01/24/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
01/28/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
01/30/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
01/31/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
02/04/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
02/06/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
02/07/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
02/10/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 2-10-25, top out at southwest shooting tower/column verified as per approved plans.
02/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
2-10-25, top out at southwest shooting tower/column verified as per approved plans.
2/11/25: reinforcement per plan at 4 light pole cages at shooting range
02/13/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
2-10-25, top out at southwest shooting tower/column verified as per approved plans.
2/11/25: reinforcement per plan at 4 light pole cages at shooting range
2/13/25: reinforcement per plan at first list at virtual training room 0'-5'.
02/18/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
2-10-25, top out at southwest shooting tower/column verified as per approved plans.
2/11/25: reinforcement per plan at 4 light pole cages at shooting range
2/13/25: reinforcement per plan at first lift at virtual training room 0'-5'.
2/18/25: reinforcement per plan at first lift at class room 0"-5'.
02/21/2025 COT - HCBU - Excavation/Rebar/Zoning  Canceled 2-21-25, canceled by contractor.
02/26/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
2-10-25, top out at southwest shooting tower/column verified as per approved plans.
2/11/25: reinforcement per plan at 4 light pole cages at shooting range
2/13/25: reinforcement per plan at first lift at virtual training room 0'-5'.
2/18/25: reinforcement per plan at first lift at class room 0"-5'.
2-21-25, canceled by contractor.
2/26/25: reinforcement per plan at shooting tower pad and footings.
03/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
2-10-25, top out at southwest shooting tower/column verified as per approved plans.
2/11/25: reinforcement per plan at 4 light pole cages at shooting range
2/13/25: reinforcement per plan at first lift at virtual training room 0'-5'.
2/18/25: reinforcement per plan at first lift at class room 0"-5'.
2-21-25, canceled by contractor.
2/26/25: reinforcement per plan at shooting tower pad and footings.
3/3/25: 2nd lift at class rooms reinforced per plans
03/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2
1/2/25: classroom rebar reinforcement per plan at stem wall. Ok to fully grout
1/10/25: drilled shaft foundation for (7) steel columns at GL SA/S1-S7 per plans. Ok to proceed with concrete placement.
1/24/25: reinforcement per plan at second lift at shooting range canopy tower columns.
1/28/25: reinforcement per plan at stem wall @ classrooms.
1/30/25: reinforcement at slab at training room/ classroom per plan ok to proceed.
1/31/25: reinforcement per plan at third lift at shooting range canopy tower columns.
2/4/25: reinforcement per plans at 4th lift at shooting range canopy tower columns.
2/6/25: top out at Shooting range canopy tower (3) columns
2/7/25: third lift at south west tower at shooting range canopy column
2-10-25, top out at southwest shooting tower/column verified as per approved plans.
2/11/25: reinforcement per plan at 4 light pole cages at shooting range
2/13/25: reinforcement per plan at first lift at virtual training room 0'-5'.
2/18/25: reinforcement per plan at first lift at class room 0"-5'.
2-21-25, canceled by contractor.
2/26/25: reinforcement per plan at shooting tower pad and footings.
3/3/25: 2nd lift at class rooms reinforced per plans
3/11/25: 3rd lift at class rooms reinforced per plans ok to proceed.
03/17/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3-17-24, cmu top out for classrooms at 16'-okay for grout.
03/25/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 3-25-25, shooting platform level 2 reinforcement/preslab per plans. Okay to pour at concrete at decking.
07/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed
07/25/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed 7-25-25: previously inspected and approved.
11/19/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 11/19/24: reinforcement per plan at Virtual training foundation at GL A-D/1-3 ok to proceed with concrete placement in footings.
12/20/24: reinforcement per plan at footings (2)F3, (2) F4 and (1) F2