Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 04/29/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
4-29-25, in wall electrical intermediate at virtual classrooms per plan. Okay to insulate walls and continue with construction at progress areas. |
| 05/19/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
5-19-25, electrical,mechanical,plumbing above ceiling together with suspended ceiling framing in virtual classroom verified per plans. Okay to apply insulation at progress areas. |
| 07/25/2025 |
COT - HCEL - Electrical Intermediate |
|
Passed |
7-25-25: approved. |