Permit: TC-COM-1222-00252

Parcel: 11941176H


Addresses:

1775 W AJO WY

Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Progress  

Date Description Inspector Results Comments
07/06/2023 COT - HCEL - Electrical Progress   Partial Pass 7-6-23: South restrooms, theater, and playroom.
07/12/2023 COT - HCEL - Electrical Progress   Partial Pass
07/20/2023 COT - HCEL - Electrical Progress   Partial Pass south restrooms in wall and OH ok for drywall
07/25/2023 COT - HCEL - Electrical Progress   Not Ready
07/27/2023 COT - HCEL - Electrical Progress   Partial Pass south wall children’s theater ok to drywall and above ceiling rooms 116, 117, 118, 111,and 110
08/01/2023 COT - HCEL - Electrical Progress   Partial Pass
08/16/2023 COT - HCEL - Electrical Progress   Partial Pass 8/16/2023 boys restroom room number 141 okay to proceed with hard lids. Room 108 intermediates okay to proceed.
09/05/2023 COT - HCEL - Electrical Progress   Partial Pass 9/5/23: above ceiling electrical for cafe on east side of building, electrical in knee walls in children's theater east and west ok to proceed
09/11/2023 COT - HCEL - Electrical Progress   Partial Pass North porch. and Cafe Janitors closet.
09/14/2023 COT - HCEL - Electrical Progress   Partial Pass 7-6-23: South restrooms, theater, and playroom.
7/12/23: Main Street (Area) floor box trenches okay to fill and concrete

Walls for restrooms, storage, theater, kitchen and laundry.

8/16/2023 boys restroom room number 141 okay to proceed with hard lids. Room 108 intermediates okay to proceed.

9/5/23: above ceiling electrical for cafe on east side of building, electrical in knee walls in children's theater east and west ok to proceed

North porch and Cafe Janitors closet.

9/14/23: electrical under stage ok to proceed
09/20/2023 COT - HCEL - Electrical Progress   Partial Pass 7-6-23: South restrooms, theater, and playroom.
7/12/23: Main Street (Area) floor box trenches okay to fill and concrete

Walls for restrooms, storage, theater, kitchen and laundry.

8/16/2023 boys restroom room number 141 okay to proceed with hard lids. Room 108 intermediates okay to proceed.

9/5/23: above ceiling electrical for cafe on east side of building, electrical in knee walls in children's theater east and west ok to proceed

North porch and Cafe Janitors closet.

9/14/23: electrical under stage ok to proceed

9/20/23: foh sound sanctuary electrical under platform per plan, Unisex restroom #104 in wall electrical per plan. Missing wiring for light fixture.
09/25/2023 COT - HCEL - Electrical Progress   Partial Pass 7-6-23: South restrooms, theater, and playroom.
7/12/23: Main Street (Area) floor box trenches okay to fill and concrete

Walls for restrooms, storage, theater, kitchen and laundry.

8/16/2023 boys restroom room number 141 okay to proceed with hard lids. Room 108 intermediates okay to proceed.

9/5/23: above ceiling electrical for cafe on east side of building, electrical in knee walls in children's theater east and west ok to proceed

North porch and Cafe Janitors closet.

9/14/23: electrical under stage ok to proceed

9/20/23: foh sound sanctuary electrical under platform per plan, Unisex restroom #104 in wall electrical per plan. Missing wiring for light fixture.

9/25/23: electrical above ceiling (light fixtures only) complete in rooms 108,109A,173,113,123,121,122,174,133,132,130,129,128,127,124,125,126,130a,131,134b,135
10/04/2023 COT - HCEL - Electrical Progress   Partial Pass Conference room #171, break room #165, north wall reception front desk across from lobby room #170, unisex room # 152 men’s restroom #154, women’s restroom #155. Men room #163 women’s room #162. Okay for drywall. Okay to proceed progress areas. 10/4/2023
10/11/2023 COT - HCEL - Electrical Progress   Partial Pass Building D east half of building all electrical above ceiling okay to proceed with grid. 10/11/2023
10/17/2023 COT - HCEL - Electrical Progress   Not Ready
10/31/2023 COT - HCEL - Electrical Progress   Passed