Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - HCBU - Building Final | Re-inspection required | 6/5/23: Not ready for final inspection. Electric incomplete, panels incomplete, label all breakers area specific, bathrooms incomplete, remove all construction debris. Waiting on Fire Dept and Engineering to complete their final inspection. | ||
| 06/08/2023 | COT - HCBU - Building Final | Partial Pass | 6/5/23: Not ready for final inspection. Electric incomplete, panels incomplete, label all breakers area specific, bathrooms incomplete, remove all construction debris. Waiting on Fire Dept and Engineering to complete their final inspection. 6/8/23: install approximately 10 interior doors & the glazing in the recording studio. OK to issue TCO Level 4. |
|
| 07/07/2023 | COT - HCBU - Building Final | Passed |