Inspection Status: Partial Pass

Inspection History: COT - CSOL - Electrical Underground Solar Project

Date Description Inspector Results Comments
02/23/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass Underground trench from column A to column F. Electric conduits at 1” - 2’ in trench; concrete placed in trench.
02/27/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 2.26.26
trench/conduit approved at progress areas, proceed Partial pass
03/03/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 3.3.26
Partial for canopy E ufer
03/04/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass 3.4.26
Partial pass for c and d
03/04/2026 COT - CSOL - Electrical Underground Solar Project Passed
03/05/2026 COT - CSOL - Electrical Underground Solar Project Partial Pass Partial pass canopy b
03/09/2026 COT - CSOL - Electrical Underground Solar Project Passed Passed for final canopy 3/9/26