Parcel: 11504505A


Addresses:

812 E SPEEDWAY BL


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-1124-02144

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
05/01/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil beams in place at GL: A/7-10
05/06/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil beam caissons at GL: A/10 - 3. Caisson numbers #12 - 33, 35 - 36
05/08/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil beams at GL: C - E/ 1 -10. Caissons; 38, 40, 41, 45, 47, 52. Ok to place grout in progress areas.
05/09/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil beams at GL: E - G/1 - 4; 7 added caissons that were not numbered on plans. Ok to place concrete in progress areas.
05/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soils on D Wall: GL: E/7 - 12: mail #’s. 75 - 95. Ok to place grout 9n progress areas.
05/16/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails at GL: A - C/1 -10, B - E/1 - 21, nails 1 - 28; D - A/1 - 2, E/4 - 7; nails 29 - 74. Ok to place grout in progress areas and wire mesh with slurry coating.
05/20/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wire mesh for shot-Crete at Gl: A - E/4 - 1; E/1 - 7; A/5 - 10. OK to,place shot-Crete in progress areas.
05/22/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails, casing portion of system at GL: A - 1-/B -12; #116, 117, 118, 119, 120, 121, 122, 123.
05/28/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails and shot-Crete placement for soil beams at GL: E/1 - 4, 1/E - D, A/2 - 7.
05/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails drilled and grouted at GL: E/12 - 11 for 28 May; #291, 192, 261, 264. 29 May soil nails drilled and grouted at GL: E/11 - 7, #260, 187, 188, 256, 257, 181, 184, 182, 183, 251, 171.
06/03/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails shot-crete at GL: D/1 - 12. Ok to,place grout in,progress areas
06/05/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails shot Crete at GL: 11/D - E. To be random tension testing throughout.
06/09/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails at GL: A - B/10, B/11.5 - 10 (7 nails drilled). Note: Soil nail drilling has been completed as,of this date.
06/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Soil nails stress testing (partial) at GL: 1/A - E
06/24/2025 COT - HCBU - Excavation/Rebar/Zoning  Passed