Inspection Status: Partial Pass
Inspection History: COT - HCBU - Stem Wall/Retaining Wall
| Date |
Description |
Inspector |
Results |
Comments |
| 05/02/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Soil beams inserted at GL: A/10-13. |
| 05/20/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Wire mesh placement for retaining wall at GL: A - E/1 - 4; E/1 - 7; A/5 - 10. OK to place shot-Crete in progress areas. |
| 06/04/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Soil nails shot-Crete at GL: A/1 - 12. |
| 06/06/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Partial Pass |
Soil nails shot-Crete at GL: D/5 - 7. OK to cover progress areas. |
| 06/24/2025 |
COT - HCBU - Stem Wall/Retaining Wall |
|
Passed |
|