Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - TC-COM-1124-02135
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/26/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6-26-25: reinforcement on perimeter footing (F1) verified per plans. Okay to pour at progress areas. | |
| 07/10/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Stemwall | |
| 07/15/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | West wall column footings (4 each); East wall column footings gs (4each). Ok to place concrete in progress areas. | |
| 07/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | North and South stem walls at 12” x 8”. Ok to place concrete in progress areas. | |
| 07/31/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Northeast corner of structure; footing for stem wall at approximately 25 feet. Ok to place concrete in progress area. | |
| 08/07/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Six light pole bases n North and East sides. | |
| 08/13/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Stem wall footing at Northeast portion of slab area, approximately 50’. Ok to set forms and place concrete. | |
| 08/20/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Stem wall footing at main entry area (Northeast corner of structure), approximately 45’. Ok to place concrete in progress area. | |
| 09/02/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 9/2/25: reinforcement per approved plans at SW loading dock footers. Ok to proceed with concrete placement. | |
| 09/18/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Center East end (store front) of building remainder of exterior steel stud wall footing and concrete turndown at building edge. Detail 104 & 111. Okay for concrete placement. 9/18/2025 | |
| 09/24/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Southwest service ramp. Ok to set rebar and place forms for ramp walls. | |
| 09/29/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Southwest ramp and stair areas. | |
| 10/06/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Rebar placed in walls of trash enclosure. | |
| 10/15/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 10/15/25 Partial pass, SW walls. . |
|
| 10/21/2025 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | ||
| 10/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Passed | balance of light poles and 60’ of UG Electric North of East pole. |