Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 10/06/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Trash enclosure at 6’, OK to place grout in progress areas: clean outs punched at slab level. |
| 10/21/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1st Lift of veneer. |
|
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
10-28-25: reinforcement at east, south, north, west veneer block wall verified per plans. Okay to grout 2nd lift at 4' aff. |
| 11/04/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Southeast and Northwest corners at 5’4” second lift. Ok to grout progress areas. |
| 11/12/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
|
| 11/17/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
11/17/2025 partial pass. Southwest and north east corners approved at top out. Okay to grout progress areas. |
| 11/21/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
11/21/25: 6' lift at 6" CMU wall at south west corner of building. Reinforcement per approved plans ok to proceed with grout |
| 11/25/2025 |
COT - HCBU - Masonry Pregrout |
|
Passed |
Southwest portion,of building; decorative block topped out at 19’ 4”. Ok to place grout in progress areas. |