| 06/17/2024 | COT - HCBU - Building Progress | Partial Pass | ||
| 06/18/2024 | COT - HCBU - Building Progress | Partial Pass | Partial approval for first floor only. Partial for TCO level three first floor only, construction barrier required on first floor stairs and elevator. Water Chlorination report is applicable to second floor only. Not required for first floor TCO. |
|
| 08/06/2024 | COT - HCBU - Building Progress | Not Ready | Meeting to discuss demo | |
| 09/06/2024 | COT - HCBU - Building Progress | Partial Pass | From grid line 4 to the east East above ceiling complete, label VAV disconnects please verify barometric dampers are installed in functioning to rooftop down shots in two locations on the east side at final | |
| 11/12/2024 | COT - HCBU - Building Progress | Passed |