Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 06/27/2023 |
BULD - Electrical Clearance |
|
Partial Pass |
No power required for canopy until August 2-23. |
| 10/30/2023 |
BULD - Electrical Clearance |
|
Passed |
Electric for canopies is complete. No clearance required. Power is,drawn from building. |
| 11/09/2023 |
BULD - Electrical Clearance |
|
Passed |
|
| 11/15/2023 |
BULD - Electrical Clearance |
|
Passed |
No clearance required |
| 11/15/2023 |
BULD - Electrical Clearance |
|
Passed |
No clearance required. |