Parcel: 11918030A

Inspection Status: Partial Pass

Inspection History: COT - LCBU - Masonry Pregrout 

Permit Number - TC-COM-1122-00070

Inspection Description - COT - LCBU - Masonry Pregrout 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/08/2024 COT - LCBU - Masonry Pregrout  Partial Pass ok for 1st lift on north wall
01/18/2024 COT - LCBU - Masonry Pregrout  Partial Pass 1/18/24 East side 14 panels from north to south and north side 5 panels ok for first lift grout
2nd lift approximately 80' ok for grout
Top out on northwest corner west to east approximately 8 panels and return to south ok for grout
01/30/2024 COT - LCBU - Masonry Pregrout  Partial Pass 1/18/24 East side 14 panels from north to south and north side 5 panels ok for first lift grout
2nd lift approximately 80' ok for grout
Top out on northwest corner west to east approximately 8 panels and return to south ok for grout
1/30/24: northeast corner to east wall second lift approximately 100' stretch ok to grout reinforcement per plan.
02/16/2024 COT - LCBU - Masonry Pregrout  Partial Pass
02/22/2024 COT - LCBU - Masonry Pregrout  Not Ready no call back from contractor
03/06/2024 COT - LCBU - Masonry Pregrout  Partial Pass
03/19/2024 COT - LCBU - Masonry Pregrout  Partial Pass 1/18/24 East side 14 panels from north to south and north side 5 panels ok for first lift grout
2nd lift approximately 80' ok for grout
Top out on northwest corner west to east approximately 8 panels and return to south ok for grout
1/30/24: northeast corner to east wall second lift approximately 100' stretch ok to grout reinforcement per plan.
2/16/24 east wall 2nd lift approximately 216 ft mid span
3/19/24: East wall ok to grout complete. Reinforcement per plan top out at East wall.
04/05/2024 COT - LCBU - Masonry Pregrout  Partial Pass 1/18/24 East side 14 panels from north to south and north side 5 panels ok for first lift grout
2nd lift approximately 80' ok for grout
Top out on northwest corner west to east approximately 8 panels and return to south ok for grout
1/30/24: northeast corner to east wall second lift approximately 100' stretch ok to grout reinforcement per plan.
2/16/24 east wall 2nd lift approximately 216 ft mid span
3/19/24: East wall ok to grout complete. Reinforcement per plan top out at East wall.
4/5/24: south wall going from south east corner W3 183' going west 2nd lift per plan ok to proceed. West wall at mid way opening 52' of W1 and W2, 1st lift per plan ok to proceed.
04/17/2024 COT - LCBU - Masonry Pregrout  Partial Pass
04/23/2024 COT - LCBU - Masonry Pregrout  Partial Pass 1/18/24 East side 14 panels from north to south and north side 5 panels ok for first lift grout
2nd lift approximately 80' ok for grout
Top out on northwest corner west to east approximately 8 panels and return to south ok for grout
1/30/24: northeast corner to east wall second lift approximately 100' stretch ok to grout reinforcement per plan.
2/16/24 east wall 2nd lift approximately 216 ft mid span
3/19/24: East wall ok to grout complete. Reinforcement per plan top out at East wall.
4/5/24: south wall going from south east corner W3 183' going west 2nd lift per plan ok to proceed. West wall at mid way opening 52' of W1 and W2, 1st lift per plan ok to proceed.
4/17/24 partial approval for West wall from southwest corner to Westgate third lift
4/23/24: top out ok to grout from west gate opening 100' going south ok to grout, south wall east of South Gate opening third lift ok to grout. South wall west of South Gate opening second lift ok to grout.
05/31/2024 COT - LCBU - Masonry Pregrout  Passed