Inspection Status: Not Ready
Inspection History: COT - LCPL - Sewer
| Date |
Description |
Inspector |
Results |
Comments |
| 11/10/2025 |
COT - LCPL - Sewer |
|
Not Ready |
|
| 11/14/2025 |
COT - LCPL - Sewer |
|
Partial Pass |
Starting at first double clean outs at west gate. Heading north approximately 485’ of 4” schedule 40 pvc. Okay to backfill progress areas. Shading required. Ensure green tape is in place after first lift of backfill. 11/14/2025 |
| 11/20/2025 |
COT - LCPL - Sewer |
|
Partial Pass |
11-20-25: partial pass pending air test-verified trench depth & tracer wire on approximately 250' of 4" Schedule 40 pvc. Okay to backfill progress areas using shading materials. |
| 12/04/2025 |
COT - LCPL - Sewer |
|
Passed |
12/4/2025 tapped in to main line. Provided a cookie cut to verify a clean cut for saddle strap. Okay to backfill all progress areas. Green tape roll is in place. Shading required. |