Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 01/24/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
1st lift for site wall on south east corner of property. |
| 01/29/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
2nd lift. Site wall on south east side of property. |
| 02/04/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
East site wall topped-out at 8’ and capped. Footings for patio cover are dry packed per plan. Ok to cover column plates up to 3 inches of material and cover the remaining areas with concrete. East side of building at 10’ opening; lintel has been dry-packed at 10’ to 11’ at both ends of the lintel. |
| 03/05/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
drypack on lentils on new saw cut openings |
| 09/26/2025 |
COT - HCBU - Masonry Pregrout |
|
Passed |
|