Inspection Status: Re-inspection required
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 08/08/2025 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
8-8-25: in wall plumbing -firefoam all penetrations, secure pex and DWV with straps above all blocking. |
| 08/12/2025 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
8-12-25: secure DWV at west wall every 4', firefoam DWV penetrations at west side and firefoam horizontal penetration at south wall where metal conduit and DWV penetrates wall-all penetrations from an unconditioned space to a conditioned space require firefoam, add Boca plate and strap to DWV at electrical room, extend DWV through roof at electrical room and firefoam penetrations. |
| 08/13/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
8-13-25: plumbing corrections made at interior side of building. Okay to continue with construction. |
| 11/14/2025 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
11-14-25: approved. |