Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 07/01/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
Partial pass. Electrical underground in slab approved. Okay to backfill progress areas. Shading required. 7/1/2025 |
| 09/08/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
9-8-25: excavation & reinforcement verified per detail SP2.0/10. Conduit/bare copper verified in place. Okay to pour 9 light pole bases. |
| 09/08/2025 |
COT - HCEL - Electrical Progress |
|
Partial Pass |
9-8-25: total of 9 light pole cages. Excavation on 3 not per plan depth. 2 located at midway point of west side and 1 located on the east northeast corner of site. Okay to pour on other 6 but a reinspect is required for those that failed. |
| 11/14/2025 |
COT - HCEL - Electrical Progress |
|
Passed |
11-14-25: approved. |