Inspection Status: Partial Pass
Inspection History: COT - HCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 03/28/2025 |
COT - HCPL - Rough Soil |
|
Partial Pass |
3-28-25, approved plans call for an ejector pump but a change by the architect has been made from pump to a lavatory instead. Submit a revision to the city for review outlining change. Okay to pour concrete at own risk. |
| 04/03/2025 |
COT - HCPL - Rough Soil |
|
Partial Pass |
Plumbing in slab approved for room number #217. Okay to proceed progress areas. Shading required. 4/3/2025 |
| 04/09/2025 |
COT - HCPL - Rough Soil |
|
Partial Pass |
Mop sink in existing equipment room and lavatory in vault room. Okay to backfill progress areas. Shading required. 4/9/2024 |
| 07/23/2025 |
COT - HCPL - Rough Soil |
|
Passed |
|