Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 04/09/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
As built plans will be submitted on new sewer line. Tie in to main sewer line. Managers suite #126, Restroom ADA #122, community room #121, laundry room #130, mechanical room #131, storage room #131. Partial pending lint trap. Okay to backfill progress areas. Shading is required. 4/9/2025 |
| 04/17/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Lint trap in laundry room #130 on test. Okay to backfill. 4/17/2025 |
| 04/18/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
Partial pass. All of first floor UG plumbing approved. Okay to backfill all progress areas. 4/18/2025 |
| 04/28/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
|
| 05/05/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
|
| 05/08/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
|
| 05/09/2025 |
COT - HCPL - Plumbing Progress |
|
Partial Pass |
|
| 06/09/2025 |
COT - HCPL - Plumbing Progress |
|
Not Ready |
|
| 06/10/2025 |
COT - HCPL - Plumbing Progress |
|
Passed |
|