Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCME - Mechanical Above Ceiling
Permit Number - TC-COM-1023-02346
Inspection Description - COT - HCME - Mechanical Above Ceiling
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/01/2024 | COT - HCME - Mechanical Above Ceiling | Not Ready | ||
04/19/2024 | COT - HCME - Mechanical Above Ceiling | Partial Pass | ||
06/10/2024 | COT - HCME - Mechanical Above Ceiling | Partial Pass | Partial approval, please adjust hangers at elbows and one joint is not sealed Partial approval for room 105 6/10/24: room 5 complete |
|
06/11/2024 | COT - HCME - Mechanical Above Ceiling | Re-inspection required | Partial approval, please adjust hangers at elbows and one joint is not sealed Partial approval for room 105 6/10/24: room 5 complete 6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps. |
|
06/12/2024 | COT - HCME - Mechanical Above Ceiling | Partial Pass | Partial approval, please adjust hangers at elbows and one joint is not sealed Partial approval for room 105 6/10/24: room 5 complete 6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps. 6/12/24: room 104 partial pass (pending middle span of tiles) |
|
06/13/2024 | COT - HCME - Mechanical Above Ceiling | Re-inspection required | Partial approval, please adjust hangers at elbows and one joint is not sealed Partial approval for room 105 6/10/24: room 5 complete 6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps. 6/12/24: room 104 partial pass (pending middle span of tiles) 6/13/24: seismic wire missing for grid ceiling supports. Seal all penetrations at fire wall throughout. |
|
06/14/2024 | COT - HCME - Mechanical Above Ceiling | Not Ready | Partial approval, please adjust hangers at elbows and one joint is not sealed Partial approval for room 105 6/10/24: room 5 complete 6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps. 6/12/24: room 104 partial pass (pending middle span of tiles) 6/13/24: seismic wire missing for grid ceiling supports. Seal all penetrations at fire wall throughout. 6/14/24: not ready |
|
06/18/2024 | COT - HCME - Mechanical Above Ceiling | Passed |