Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 14029003H


Addresses:

3400 E BRITANNIA DR


Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Above Ceiling 

Permit Number - TC-COM-1023-02346

Inspection Description - COT - HCEL - Electrical Above Ceiling 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
04/19/2024 COT - HCEL - Electrical Above Ceiling  Partial Pass
06/10/2024 COT - HCEL - Electrical Above Ceiling  Partial Pass Partial approval for room 105
6/10/24: room 5 complete
06/12/2024 COT - HCEL - Electrical Above Ceiling  Partial Pass Partial approval for room 105
6/10/24: room 5 complete
6/12/24: 104 ok to lay tile (pending 6 tiles midway)
06/13/2024 COT - HCEL - Electrical Above Ceiling  Re-inspection required Partial approval for room 105
6/10/24: room 5 complete
6/12/24: 104 ok to lay tile (pending 6 tiles midway)
Partial approval, please adjust hangers at elbows and one joint is not sealed
Partial approval for room 105
6/10/24: room 5 complete
6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps.
6/12/24: room 104 partial pass (pending middle span of tiles)
6/13/24: seismic wire missing for grid ceiling supports. Seal all penetrations at fire wall throughout.
06/14/2024 COT - HCEL - Electrical Above Ceiling  Not Ready Partial approval for room 105
6/10/24: room 5 complete
6/12/24: 104 ok to lay tile (pending 6 tiles midway)
Partial approval, please adjust hangers at elbows and one joint is not sealed
Partial approval for room 105
6/10/24: room 5 complete
6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps.
6/12/24: room 104 partial pass (pending middle span of tiles)
6/13/24: seismic wire missing for grid ceiling supports. Seal all penetrations at fire wall throughout.
Partial approval, please adjust hangers at elbows and one joint is not sealed
Partial approval for room 105
6/10/24: room 5 complete
6/11/24: seismic wire missing at A/C diffusers, MC cable must be properly supported, Flex duct must be supported by saddle straps.
6/12/24: room 104 partial pass (pending middle span of tiles)
6/13/24: seismic wire missing for grid ceiling supports. Seal all penetrations at fire wall throughout.
6/14/24: not ready
06/18/2024 COT - HCEL - Electrical Above Ceiling  Passed