Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/21/2026 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | ||
| 06/02/2026 | COT - HCBU - Excavation/Rebar/Zoning | Re-inspection required | Remove loose fill dirt. Add rebar south east corner. Provide 3" min earth clearance. 6/2/2026 | |
| 06/04/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6/4/26: elevator hoistway footer/pad per approved plans ok to proceed with concrete placement, steel column footing at GL A/5 per approved plans ok to proceed with concrete placement. | |
| 06/12/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Partial pass. 1st lift For elevator hoistway walls. Okay to grout progress areas. 6/12/2026 | |
| 07/13/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 7/13/2026 Partial pass, Drawing 109 for stair 2 column and daypack and sonotube detail (north east corner of tower) Drawing 112 for stair 1 column dry pack under column base (north west corner of tower) Stair two dry pack pre sono tube |