| 01/21/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Re-inspection required |
1-21-26: plans call for #4 @ 16" o.c. But the section located at north end appears to have a slab on top of another slab with the top slab containing a thickness of 2" on one side and a 1" thickness on other end. Adding # 4 rebar will not work-submit a revision to the city showing correction-city approval is required. |
| 01/22/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1-22-26: reinforcement for concrete pad at extended sport court verified per SP-keynote #13 & revision submitted to the city on north side which calls for #3's @18" o.c.-set-3G Epoxy 3" embed.. okay for concrete placement at own risk pending city approval. |