Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Underground
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/16/2026 | COT - LCEL - Electrical Underground | Partial Pass | 03/16/2026 UFER in place. Partial pass pending conduit trench to transformer. |
|
| 09/18/2026 | COT - LCEL - Electrical Underground | Partial Pass | 9/18/26: partial pass on a 4" underground schedule 40 electrical conduit stemming from transformer. Conduit will eventually lead to Building 23's main panel. Okay to backfill progress areas. | |
| 09/23/2026 | COT - LCEL - Electrical Underground | Partial Pass | 9/23/2026 4” schedule 40. Total of three for the secondaries going to each of the building. From transformer location about 20’ in of the edge of curb. Okay to backfill progress areas. Shading required. Ensure caution tape is in place after first lift of compaction. | |
| 09/24/2026 | COT - LCEL - Electrical Underground | Passed | 09/24/2026 Picked up remaining 250' run of 4" sch 40 conduit from near street and transformer to building, trench depth approximately 5'. Okay to backfill, caution burial tape and shading required. |