| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/13/2024 | COT - HCBU - Building Progress | Partial Pass | 3/13/24: footing at thickened slab at bearing wall reinforcement per plan, footing at existing demising wall per plan, reinforcement at footings for stairs per plan ok to pour. | |
| 09/04/2024 | COT - HCBU - Building Progress | Re-inspection required | 3/13/24: footing at thickened slab at bearing wall reinforcement per plan, footing at existing demising wall per plan, reinforcement at footings for stairs per plan ok to pour. Please secure line sets and put seismic wires on diffusers were required Unit on 2nd floor it should require a filter frame ok to install ceiling tiles 9/4/24: called and received no answer, arrived on site and had no access to site. |
|
| 09/25/2024 | COT - HCBU - Building Progress | Passed |