Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Date Description Inspector Results Comments
03/13/2024 COT - HCBU - Building Progress Partial Pass 3/13/24: footing at thickened slab at bearing wall reinforcement per plan, footing at existing demising wall per plan, reinforcement at footings for stairs per plan ok to pour.
09/04/2024 COT - HCBU - Building Progress Re-inspection required 3/13/24: footing at thickened slab at bearing wall reinforcement per plan, footing at existing demising wall per plan, reinforcement at footings for stairs per plan ok to pour.
Please secure line sets and put seismic wires on diffusers were required
Unit on 2nd floor it should require a filter frame ok to install ceiling tiles
9/4/24: called and received no answer, arrived on site and had no access to site.
09/25/2024 COT - HCBU - Building Progress Passed