Parcel: 117130410


Addresses:

20 E OCHOA ST


Inspection Status: Partial Pass

Inspection History: COT - HCBU - Building Progress

Permit Number - TC-COM-0923-02239

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/16/2026 COT - HCBU - Building Progress Partial Pass 1/16/2026 6th floor all bathrooms above ceiling approved. Okay to proceed progress areas.
02/06/2026 COT - HCBU - Building Progress Partial Pass 2/6/26: TCO discussion and requirements
02/23/2026 COT - HCBU - Building Progress Canceled Superintendent requested Gustavo for TCO walk-through. Will reschedule for 24 FEBRUARY.
02/25/2026 COT - HCBU - Building Progress Re-inspection required 2/25/26: P-trap required at all air handlers for condensate drain disposal, secondary drain required per IMC 307.2.3, properly terminate and support dishwasher high rise loop, ensure marking on air handlers indicate which heat kit if any is installed, smoke detectors shall be relocated to meet code requirements, panel schedules shall be updated to ensure all circuits are correct. Vertical grab bar required in ada bathtub,. Other items may be added.
03/02/2026 COT - HCBU - Building Progress Re-inspection required 3/2/26: pending vertical grab bar at ADA units on first floor, pending Appeal approval for smoke detectors, pending updated panel schedule for all units, GFCI in restroom required in unit 106, dishwasher not installed in apple room,
03/12/2026 COT - HCBU - Building Progress Re-inspection required 3/12/26: receptacle spacing at kitchen counter top shall be no more than 24" from edge. Counter top 12" or greater requires receptacle, seal all flex duct connections at air handler room and install overflow switch. For 1st,2nd and 3rd floors. adjust door openers to no more than 5 pounds of force
03/14/2025 COT - HCBU - Building Progress Partial Pass 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed.
6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
03/16/2026 COT - HCBU - Building Progress Partial Pass 3/16/26: receptacle spacing at kitchen counter top shall be no more than 24" from edge. Counter top 12" or greater requires receptacle, seal all flex duct connections at air handler room and install overflow switch. For 1st,2nd,3rd and 4th floor
COT - HCBU - Building Progress Scheduled
03/26/2025 COT - HCBU - Building Progress Partial Pass Informational inspection for Level #1, North portion of building. Please check with architect for height of door jambs at room entry areas.
04/04/2025 COT - HCBU - Building Progress Partial Pass 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed.
6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
4/4/25: Progress inspection for first framing
04/08/2025 COT - HCBU - Building Progress Partial Pass Level #2; Ok to seal coat deck with elasto-metric.
04/17/2025 COT - HCBU - Building Progress Partial Pass 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed.
6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
4/4/25: Progress inspection for first framing
4/17/25: first floor insulation inspection at ceiling.
04/24/2025 COT - HCBU - Building Progress Partial Pass Sheetrock nailing for laundry room, Ok to tape and texture progress areas.
04/28/2025 COT - HCBU - Building Progress Partial Pass Level #1 sheet rock ceilings; Ok to patch and tape progress areas. Level #2; Fire caulking ceiling areas. Ok to cover progress areas.
04/29/2025 COT - HCBU - Building Progress Partial Pass Sheet rock nailing on Level #1, room ceilings in #104, 105, 106, 107; laundry room ceiling and walls. Level #1 corridor walls - first layer, Ok to tape and patch progress areas.
05/01/2025 COT - HCBU - Building Progress Partial Pass Level #1 corridor walls second layer of sheet rock. Ok to,tape progress areas.
05/08/2025 COT - HCBU - Building Progress Canceled Contractor cancelled.
05/22/2025 COT - HCBU - Building Progress Partial Pass 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed.
6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
4/4/25: Progress inspection for first framing
4/17/25: first floor insulation inspection at ceiling.
5/22/25: second floor 1/2" type x drywall at demising walls partial pass one side. Pending both sides of demising walls
05/30/2025 COT - HCBU - Building Progress Partial Pass Screw inspection for corridor ceiling on level #2, corridor walls are not ready. Level #3 corridor walls at rooms 305 - 311 and corridor ceiling with metal sheathing.
06/03/2025 COT - HCBU - Building Progress Partial Pass Partial pass. Framing at all shaft walls 3rd floor per plan. Okay to proceed progress areas. 6/3/2025
06/10/2025 COT - HCBU - Building Progress Partial Pass Level #2, corridor walls and ceilings (sheet rock). Ok to,tape progress areas.
06/12/2025 COT - HCBU - Building Progress Partial Pass Level #1; demising walls in room units: Fire caulked and fire foamed. Ok to cover progress areas.
06/23/2025 COT - HCBU - Building Progress Partial Pass Level #3; corridor walls and ceilings framed. Ok to cover walls and ceilings. Level #4, Room units: hold downs are in place for all room units.
06/25/2025 COT - HCBU - Building Progress Partial Pass Level #3, Room units 401 - 412: floor level hold-downs. Hold-downs from Level,#4 to Level #5 are not in place.
07/02/2025 COT - HCBU - Building Progress Partial Pass Level #1, domestic waste and venting lines in,room,units. In wall,insulation,in room units; ok to cover,walls. RC channel in room unit ceilings; Ok to insulate and sheet rock ceilings. Door straps above doors and room shafts are in,-lace.
07/10/2024 COT - HCBU - Building Progress Partial Pass 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed.
07/10/2025 COT - HCBU - Building Progress Partial Pass Level #6; room units hold downs.
07/21/2025 COT - HCBU - Building Progress Partial Pass Hold-downs (room units) at Levels #6 -7)
07/28/2025 COT - HCBU - Building Progress Partial Pass In wall electric and plumbing at Level #2, Room units #210 - 213. Ensure low voltage cabinets are properly secured.
08/04/2025 COT - HCBU - Building Progress Partial Pass Level #3, room units 301 - 313, in wall electric and above ceiling electric.
08/18/2025 COT - HCBU - Building Progress Partial Pass 8/18/25: TCO consultation
08/20/2025 COT - HCBU - Building Progress Partial Pass 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed.
6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
4/4/25: Progress inspection for first framing
4/17/25: first floor insulation inspection at ceiling.
5/22/25: second floor 1/2" type x drywall at demising walls partial pass one side. Pending both sides of demising walls

Partial pass. Framing at all shaft walls 3rd floor per plan. Okay to proceed progress areas. 6/3/2025
8/18/25: TCO consultation
8/20/25: 4th floor in-wall electrical and above ceiling approved. Ok to proceed.
09/16/2024 COT - HCBU - Building Progress Partial Pass Scheduling information only.
09/17/2024 COT - HCBU - Building Progress Partial Pass Information only for scheduling inspections.
09/23/2025 COT - HCBU - Building Progress Re-inspection required 9/23/2025 provide bracing throughout along with isolators through metal framing due to protection of the pipe. Secure pex with isolators to metal braces. (4th floor)
09/25/2025 COT - HCBU - Building Progress Partial Pass Mechanical above ceiling; Level #2 Room units 201 - 213. Level #5, Room units 501 - 513 for electric rough in for in wall service.
10/08/2025 COT - HCBU - Building Progress Partial Pass Electric intermediate; Level #6, in wall electric for rooms 601 - 613.
10/15/2025 COT - HCBU - Building Progress Partial Pass Level #5, in wall waste and vent lines in units 501 - 513. Level #3; above ceilings in bathrooms and pantries in units 301 - 313. Ok to close ceilings.
10/30/2025 COT - HCBU - Building Progress Partial Pass In wall electric at Level #7: room units 701 - 713; Electric above ceiling on Level #1, corridors and room units.
11/10/2025 COT - HCBU - Building Progress Partial Pass Levels #2 & #4; corridors above ceilings. Ensure all penetrations are properly Fire caulked. Level #6, Room units 601 - 613, in wall and above ceiling plumbing. Ok to insulate and sheet rock,interior walls.
11/20/2025 COT - HCBU - Building Progress Partial Pass Plumbing intermediate: in wall plumbing in room units 701 - 713.
11/28/2025 COT - HCBU - Building Progress Not Ready
12/02/2025 COT - HCBU - Building Progress Partial Pass