Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-0923-02239
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/14/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. |
|
| 03/26/2025 | COT - HCBU - Building Progress | Partial Pass | Informational inspection for Level #1, North portion of building. Please check with architect for height of door jambs at room entry areas. | |
| 04/04/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing |
|
| 04/08/2025 | COT - HCBU - Building Progress | Partial Pass | Level #2; Ok to seal coat deck with elasto-metric. | |
| 04/17/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing 4/17/25: first floor insulation inspection at ceiling. |
|
| 04/24/2025 | COT - HCBU - Building Progress | Partial Pass | Sheetrock nailing for laundry room, Ok to tape and texture progress areas. | |
| 04/28/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1 sheet rock ceilings; Ok to patch and tape progress areas. Level #2; Fire caulking ceiling areas. Ok to cover progress areas. | |
| 04/29/2025 | COT - HCBU - Building Progress | Partial Pass | Sheet rock nailing on Level #1, room ceilings in #104, 105, 106, 107; laundry room ceiling and walls. Level #1 corridor walls - first layer, Ok to tape and patch progress areas. | |
| 05/01/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1 corridor walls second layer of sheet rock. Ok to,tape progress areas. | |
| 05/08/2025 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
| 05/22/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing 4/17/25: first floor insulation inspection at ceiling. 5/22/25: second floor 1/2" type x drywall at demising walls partial pass one side. Pending both sides of demising walls |
|
| 05/30/2025 | COT - HCBU - Building Progress | Partial Pass | Screw inspection for corridor ceiling on level #2, corridor walls are not ready. Level #3 corridor walls at rooms 305 - 311 and corridor ceiling with metal sheathing. | |
| 06/03/2025 | COT - HCBU - Building Progress | Partial Pass | Partial pass. Framing at all shaft walls 3rd floor per plan. Okay to proceed progress areas. 6/3/2025 | |
| 06/10/2025 | COT - HCBU - Building Progress | Partial Pass | Level #2, corridor walls and ceilings (sheet rock). Ok to,tape progress areas. | |
| 06/12/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1; demising walls in room units: Fire caulked and fire foamed. Ok to cover progress areas. | |
| 06/23/2025 | COT - HCBU - Building Progress | Partial Pass | Level #3; corridor walls and ceilings framed. Ok to cover walls and ceilings. Level #4, Room units: hold downs are in place for all room units. | |
| 06/25/2025 | COT - HCBU - Building Progress | Partial Pass | Level #3, Room units 401 - 412: floor level hold-downs. Hold-downs from Level,#4 to Level #5 are not in place. | |
| 07/02/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1, domestic waste and venting lines in,room,units. In wall,insulation,in room units; ok to cover,walls. RC channel in room unit ceilings; Ok to insulate and sheet rock ceilings. Door straps above doors and room shafts are in,-lace. | |
| 07/10/2024 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. | |
| 07/10/2025 | COT - HCBU - Building Progress | Partial Pass | Level #6; room units hold downs. | |
| 07/21/2025 | COT - HCBU - Building Progress | Partial Pass | Hold-downs (room units) at Levels #6 -7) | |
| 07/28/2025 | COT - HCBU - Building Progress | Partial Pass | In wall electric and plumbing at Level #2, Room units #210 - 213. Ensure low voltage cabinets are properly secured. | |
| 08/04/2025 | COT - HCBU - Building Progress | Partial Pass | Level #3, room units 301 - 313, in wall electric and above ceiling electric. | |
| 08/18/2025 | COT - HCBU - Building Progress | Partial Pass | 8/18/25: TCO consultation | |
| 08/20/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing 4/17/25: first floor insulation inspection at ceiling. 5/22/25: second floor 1/2" type x drywall at demising walls partial pass one side. Pending both sides of demising walls Partial pass. Framing at all shaft walls 3rd floor per plan. Okay to proceed progress areas. 6/3/2025 8/18/25: TCO consultation 8/20/25: 4th floor in-wall electrical and above ceiling approved. Ok to proceed. |
|
| 09/16/2024 | COT - HCBU - Building Progress | Partial Pass | Scheduling information only. | |
| 09/17/2024 | COT - HCBU - Building Progress | Partial Pass | Information only for scheduling inspections. | |
| 09/23/2025 | COT - HCBU - Building Progress | Re-inspection required | 9/23/2025 provide bracing throughout along with isolators through metal framing due to protection of the pipe. Secure pex with isolators to metal braces. (4th floor) | |
| 09/25/2025 | COT - HCBU - Building Progress | Partial Pass | Mechanical above ceiling; Level #2 Room units 201 - 213. Level #5, Room units 501 - 513 for electric rough in for in wall service. | |
| 10/08/2025 | COT - HCBU - Building Progress | Partial Pass | Electric intermediate; Level #6, in wall electric for rooms 601 - 613. | |
| 10/15/2025 | COT - HCBU - Building Progress | Partial Pass | Level #5, in wall waste and vent lines in units 501 - 513. Level #3; above ceilings in bathrooms and pantries in units 301 - 313. Ok to close ceilings. | |
| 10/30/2025 | COT - HCBU - Building Progress | Partial Pass | In wall electric at Level #7: room units 701 - 713; Electric above ceiling on Level #1, corridors and room units. | |
| 11/10/2025 | COT - HCBU - Building Progress | Partial Pass | Levels #2 & #4; corridors above ceilings. Ensure all penetrations are properly Fire caulked. Level #6, Room units 601 - 613, in wall and above ceiling plumbing. Ok to insulate and sheet rock,interior walls. | |
| 11/20/2025 | COT - HCBU - Building Progress | Partial Pass | Plumbing intermediate: in wall plumbing in room units 701 - 713. | |
| 11/28/2025 | COT - HCBU - Building Progress | Not Ready | ||
| 12/02/2025 | COT - HCBU - Building Progress | Partial Pass |