Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-0923-02239
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/16/2026 | COT - HCBU - Building Progress | Partial Pass | 1/16/2026 6th floor all bathrooms above ceiling approved. Okay to proceed progress areas. | |
| 02/06/2026 | COT - HCBU - Building Progress | Partial Pass | 2/6/26: TCO discussion and requirements | |
| 02/23/2026 | COT - HCBU - Building Progress | Canceled | Superintendent requested Gustavo for TCO walk-through. Will reschedule for 24 FEBRUARY. | |
| 02/25/2026 | COT - HCBU - Building Progress | Re-inspection required | 2/25/26: P-trap required at all air handlers for condensate drain disposal, secondary drain required per IMC 307.2.3, properly terminate and support dishwasher high rise loop, ensure marking on air handlers indicate which heat kit if any is installed, smoke detectors shall be relocated to meet code requirements, panel schedules shall be updated to ensure all circuits are correct. Vertical grab bar required in ada bathtub,. Other items may be added. | |
| 03/02/2026 | COT - HCBU - Building Progress | Re-inspection required | 3/2/26: pending vertical grab bar at ADA units on first floor, pending Appeal approval for smoke detectors, pending updated panel schedule for all units, GFCI in restroom required in unit 106, dishwasher not installed in apple room, | |
| 03/12/2026 | COT - HCBU - Building Progress | Re-inspection required | 3/12/26: receptacle spacing at kitchen counter top shall be no more than 24" from edge. Counter top 12" or greater requires receptacle, seal all flex duct connections at air handler room and install overflow switch. For 1st,2nd and 3rd floors. adjust door openers to no more than 5 pounds of force | |
| 03/14/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. |
|
| 03/16/2026 | COT - HCBU - Building Progress | Partial Pass | 3/16/26: receptacle spacing at kitchen counter top shall be no more than 24" from edge. Counter top 12" or greater requires receptacle, seal all flex duct connections at air handler room and install overflow switch. For 1st,2nd,3rd and 4th floor | |
| COT - HCBU - Building Progress | Scheduled | |||
| 03/26/2025 | COT - HCBU - Building Progress | Partial Pass | Informational inspection for Level #1, North portion of building. Please check with architect for height of door jambs at room entry areas. | |
| 04/04/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing |
|
| 04/08/2025 | COT - HCBU - Building Progress | Partial Pass | Level #2; Ok to seal coat deck with elasto-metric. | |
| 04/17/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing 4/17/25: first floor insulation inspection at ceiling. |
|
| 04/24/2025 | COT - HCBU - Building Progress | Partial Pass | Sheetrock nailing for laundry room, Ok to tape and texture progress areas. | |
| 04/28/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1 sheet rock ceilings; Ok to patch and tape progress areas. Level #2; Fire caulking ceiling areas. Ok to cover progress areas. | |
| 04/29/2025 | COT - HCBU - Building Progress | Partial Pass | Sheet rock nailing on Level #1, room ceilings in #104, 105, 106, 107; laundry room ceiling and walls. Level #1 corridor walls - first layer, Ok to tape and patch progress areas. | |
| 05/01/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1 corridor walls second layer of sheet rock. Ok to,tape progress areas. | |
| 05/08/2025 | COT - HCBU - Building Progress | Canceled | Contractor cancelled. | |
| 05/22/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing 4/17/25: first floor insulation inspection at ceiling. 5/22/25: second floor 1/2" type x drywall at demising walls partial pass one side. Pending both sides of demising walls |
|
| 05/30/2025 | COT - HCBU - Building Progress | Partial Pass | Screw inspection for corridor ceiling on level #2, corridor walls are not ready. Level #3 corridor walls at rooms 305 - 311 and corridor ceiling with metal sheathing. | |
| 06/03/2025 | COT - HCBU - Building Progress | Partial Pass | Partial pass. Framing at all shaft walls 3rd floor per plan. Okay to proceed progress areas. 6/3/2025 | |
| 06/10/2025 | COT - HCBU - Building Progress | Partial Pass | Level #2, corridor walls and ceilings (sheet rock). Ok to,tape progress areas. | |
| 06/12/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1; demising walls in room units: Fire caulked and fire foamed. Ok to cover progress areas. | |
| 06/23/2025 | COT - HCBU - Building Progress | Partial Pass | Level #3; corridor walls and ceilings framed. Ok to cover walls and ceilings. Level #4, Room units: hold downs are in place for all room units. | |
| 06/25/2025 | COT - HCBU - Building Progress | Partial Pass | Level #3, Room units 401 - 412: floor level hold-downs. Hold-downs from Level,#4 to Level #5 are not in place. | |
| 07/02/2025 | COT - HCBU - Building Progress | Partial Pass | Level #1, domestic waste and venting lines in,room,units. In wall,insulation,in room units; ok to cover,walls. RC channel in room unit ceilings; Ok to insulate and sheet rock ceilings. Door straps above doors and room shafts are in,-lace. | |
| 07/10/2024 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. | |
| 07/10/2025 | COT - HCBU - Building Progress | Partial Pass | Level #6; room units hold downs. | |
| 07/21/2025 | COT - HCBU - Building Progress | Partial Pass | Hold-downs (room units) at Levels #6 -7) | |
| 07/28/2025 | COT - HCBU - Building Progress | Partial Pass | In wall electric and plumbing at Level #2, Room units #210 - 213. Ensure low voltage cabinets are properly secured. | |
| 08/04/2025 | COT - HCBU - Building Progress | Partial Pass | Level #3, room units 301 - 313, in wall electric and above ceiling electric. | |
| 08/18/2025 | COT - HCBU - Building Progress | Partial Pass | 8/18/25: TCO consultation | |
| 08/20/2025 | COT - HCBU - Building Progress | Partial Pass | 7/10/24: reinforcement per plan at Stairwell footing at NW End on GL C/4.ok to proceed. 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed. 7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed. 3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout. 4/4/25: Progress inspection for first framing 4/17/25: first floor insulation inspection at ceiling. 5/22/25: second floor 1/2" type x drywall at demising walls partial pass one side. Pending both sides of demising walls Partial pass. Framing at all shaft walls 3rd floor per plan. Okay to proceed progress areas. 6/3/2025 8/18/25: TCO consultation 8/20/25: 4th floor in-wall electrical and above ceiling approved. Ok to proceed. |
|
| 09/16/2024 | COT - HCBU - Building Progress | Partial Pass | Scheduling information only. | |
| 09/17/2024 | COT - HCBU - Building Progress | Partial Pass | Information only for scheduling inspections. | |
| 09/23/2025 | COT - HCBU - Building Progress | Re-inspection required | 9/23/2025 provide bracing throughout along with isolators through metal framing due to protection of the pipe. Secure pex with isolators to metal braces. (4th floor) | |
| 09/25/2025 | COT - HCBU - Building Progress | Partial Pass | Mechanical above ceiling; Level #2 Room units 201 - 213. Level #5, Room units 501 - 513 for electric rough in for in wall service. | |
| 10/08/2025 | COT - HCBU - Building Progress | Partial Pass | Electric intermediate; Level #6, in wall electric for rooms 601 - 613. | |
| 10/15/2025 | COT - HCBU - Building Progress | Partial Pass | Level #5, in wall waste and vent lines in units 501 - 513. Level #3; above ceilings in bathrooms and pantries in units 301 - 313. Ok to close ceilings. | |
| 10/30/2025 | COT - HCBU - Building Progress | Partial Pass | In wall electric at Level #7: room units 701 - 713; Electric above ceiling on Level #1, corridors and room units. | |
| 11/10/2025 | COT - HCBU - Building Progress | Partial Pass | Levels #2 & #4; corridors above ceilings. Ensure all penetrations are properly Fire caulked. Level #6, Room units 601 - 613, in wall and above ceiling plumbing. Ok to insulate and sheet rock,interior walls. | |
| 11/20/2025 | COT - HCBU - Building Progress | Partial Pass | Plumbing intermediate: in wall plumbing in room units 701 - 713. | |
| 11/28/2025 | COT - HCBU - Building Progress | Not Ready | ||
| 12/02/2025 | COT - HCBU - Building Progress | Partial Pass |