Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Date Description Inspector Results Comments
01/31/2025 COT - HCBU - Excavation/Rebar/Zoning  Canceled Contractor cancelled, will reschedule for 3 February
02/04/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Interior and exterior site walls at GL: A - H, 1 -5, 1 - 5, 1 - 6, 1 - 7, 1 -8. Ok to place concrete in progress areas.
02/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Wall footings, lateral footings, columns footings, and ground beams at GL: 1 - 6/A - H. OK to place concrete in progress areas.
02/27/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Stem wall formed at GL: H/12. Ok to -lace concrete in progress areas.
03/02/2026 COT - HCBU - Excavation/Rebar/Zoning  Passed
03/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
03/18/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
318/25: 4th lift approved 24'-30'
03/24/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 9/23/24: north stairwell at 32' Above finish floor reinforcement per plan ok to proceed, elevator CMU wall at 32' Above finish floor reinforcement per plan ok to proceed.
9/24/24: North stairwell at 36' above finish floor reinforcement per plan plan ok to proceed. Elevator CMU wall at 36' above finish floor reinforcement per plan ok to proceed.
9/25/24: North stairwell at 45' above finish floor reinforcement per plan ok to proceed.
9/30/24: North stairwell at 51' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 51' above finish floor, reinforcement per plan ok to proceed.
10/1/24: North stairwell at 57' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 57' above finish floor, reinforcement per plan ok to proceed.
10/2/24: North stairwell at 63' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 63' above finish floor, reinforcement per plan ok to proceed.
10/3/24:North stairwell at 69' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 69' above finish floor, reinforcement per plan ok to proceed.
10/4/24: North stairwell at 76' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 76' above finish floor, reinforcement per plan ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
3/14/25: stair tower south reinforced per plan from 0'-4' ok to proceed with grout.
318/25: 4th lift approved 24'-30'
3/24/25: reinforcement per approved at south west stair tower. Ok to proceed with concrete placement top out at 76'8".
06/28/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
07/02/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 6/28/24: reinforcement per plan at elevator shaft slab. Ok to proceed.
7/2/24: Stair tower Mat slab @ Gridline C-E/11-13 ok to proceed.
12/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footings and column footings at GL: A - E/1 -12. OK to place concrete in progress areas.