Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
Permit Number - TC-COM-0923-02239
Inspection Description - COT - HCBU - Masonry Pregrout
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/23/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Elevator pit at 0’ - 4’, North stair stem wall at 16”, South stair stem wall at 16”: OK to grout progress areas. | |
09/16/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | North stair tower CMU Walls at 0’ - 6’2”: GL: 11 - 13/ C - D.5. Elevator at 0’ - 6’2” at GL: 6.5 - 7.5/C - D. South stair tower at GL: C - D/3 - 4: 0’ - 6’2”. OK to place grout in progress areas. | |
09/17/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | South stair tower at 6’2’ - 12’2” at GL: 11 -13/C - D; Elevator pit at 6’2’ - 12’ 2” at GL: 6.5 - /C - D. OK to place grout in progress areas. | |
09/23/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 9/23/24: north stairwell at 32' Above finish floor reinforcement per plan ok to proceed, elevator CMU wall at 32' Above finish floor reinforcement per plan ok to proceed. | |
09/24/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 9/23/24: north stairwell at 32' Above finish floor reinforcement per plan ok to proceed, elevator CMU wall at 32' Above finish floor reinforcement per plan ok to proceed. 9/24/24: North stairwell at 36' above finish floor reinforcement per plan plan ok to proceed. Elevator CMU wall at 36' above finish floor reinforcement per plan ok to proceed. |
|
09/25/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 9/23/24: north stairwell at 32' Above finish floor reinforcement per plan ok to proceed, elevator CMU wall at 32' Above finish floor reinforcement per plan ok to proceed. 9/24/24: North stairwell at 36' above finish floor reinforcement per plan plan ok to proceed. Elevator CMU wall at 36' above finish floor reinforcement per plan ok to proceed. 9/25/24: North stairwell at 45 above finish floor reinforcement per plan ok to proceed. |
|
10/04/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 9/23/24: north stairwell at 32' Above finish floor reinforcement per plan ok to proceed, elevator CMU wall at 32' Above finish floor reinforcement per plan ok to proceed. 9/24/24: North stairwell at 36' above finish floor reinforcement per plan plan ok to proceed. Elevator CMU wall at 36' above finish floor reinforcement per plan ok to proceed. 9/25/24: North stairwell at 45' above finish floor reinforcement per plan ok to proceed. 9/30/24: North stairwell at 51' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 51' above finish floor, reinforcement per plan ok to proceed. 10/1/24: North stairwell at 57' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 57' above finish floor, reinforcement per plan ok to proceed. 10/2/24: North stairwell at 63' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 63' above finish floor, reinforcement per plan ok to proceed. 10/3/24:North stairwell at 69' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 69' above finish floor, reinforcement per plan ok to proceed. 10/4/24: North stairwell at 76' above finish floor, reinforcement per plan ok to proceed, Elevator CMU wall at 76' above finish floor, reinforcement per plan ok to proceed. |