Permit: TC-COM-0923-02206

Parcel: 11611011A


Addresses:

280 N CARAPAN AV

Inspection Status: Not Ready

Inspection History: COT - LCBU - Building Progress

Date Description Inspector Results Comments
01/25/2024 COT - LCBU - Building Progress Not Ready West stairwells are not ready to waterproof. Will reschedule when ready for inspection.
02/05/2024 COT - LCBU - Building Progress Partial Pass Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
07/30/2024 COT - LCBU - Building Progress Re-inspection required Inspection is called in for lath. Okay to proceed progress areas. 2/5/2024
1/22/2024

West end add blocking where plywood meet. Shear nailing not per schedule. Add missing anchor bolts. Nail off bottom plates every 16" o.c. Add straps from headers to columns. Buildings #2 and #3. 5/2/2024

5/7/24: corrections made on west end of apartments for buildings #2 and #3.
7/25/24: through the wall metal scuppers missing throughout on all sides of building (per plan).
7/30/24: corrections not made
08/05/2024 COT - LCBU - Building Progress Passed