Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - TC-COM-0824-01601
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/14/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Column footings and wall footings at GL: 1 - 3/ A.0 - D; all rebar inclusive except for columns 3/A, 3/C, 2/C, 2/B, 2/A. Ok to place concrete in progress areas. | |
| 10/01/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Stem wall per F4 footing schedule. C1 on page S2.0 Grid line A column 2. Elevator pit stem wall footing. Per detail 106 on page S3.0. Okay for concrete placement. 10/1/2025 |
|
| 10/22/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Elevator pad footing at GL: 2/B for pedestal column; footing,(F7) at,8’ x 20’6”. Ok to place concrete in progress areas. |