Permit: TC-COM-0824-01601

Parcel: 117121940


Addresses:

72 E CONGRESS ST

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Masonry Pregrout 

Date Description Inspector Results Comments
01/27/2026 COT - HCBU - Masonry Pregrout  Partial Pass First lift (0” - 48”) for elevator shaft. Ok to place grout in progress area.
01/28/2026 COT - HCBU - Masonry Pregrout  Re-inspection required Partial passed 1/28/26 ok to proceed to next lift
02/02/2026 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft CMU walls at 9’ 4” - 13’ 4”. Inside opening for elevator car is at 8’ 9”. Ok to grout progress area.
02/04/2026 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft at Lift #5; 13’ 4” - 18’ 4”. Ok to place grout in progress areas.
02/12/2026 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft lift #6. Ok to place grout in progress areas.
02/17/2026 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft at lift #7. Ok to place grout in progress areas.
02/18/2026 COT - HCBU - Masonry Pregrout  Partial Pass Elevator shaft at lift #8. Ok to place concrete in progress area.
02/26/2026 COT - HCBU - Masonry Pregrout  Partial Pass Pre-slab inspection: South half of basement level, #4 rebar in place, plumbing has been wrapped. Ok to place concrete in progress areas.
03/12/2026 COT - HCBU - Masonry Pregrout  Partial Pass 3/12/26: Elevator shaft top out per approved plans ok to proceed with concrete placement
09/25/2025 COT - HCBU - Masonry Pregrout  Partial Pass Rebar for column (F7) at C/1.8, elevator pad at,B.T - A.5/1.5 -2. OK to place concrete in progress areas.