Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 01/27/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
First lift (0” - 48”) for elevator shaft. Ok to place grout in progress area. |
| 01/28/2026 |
COT - HCBU - Masonry Pregrout |
|
Re-inspection required |
Partial passed 1/28/26 ok to proceed to next lift |
| 02/02/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Elevator shaft CMU walls at 9’ 4” - 13’ 4”. Inside opening for elevator car is at 8’ 9”. Ok to grout progress area. |
| 02/04/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Elevator shaft at Lift #5; 13’ 4” - 18’ 4”. Ok to place grout in progress areas. |
| 02/12/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Elevator shaft lift #6. Ok to place grout in progress areas. |
| 02/17/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Elevator shaft at lift #7. Ok to place grout in progress areas. |
| 02/18/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Elevator shaft at lift #8. Ok to place concrete in progress area. |
| 02/26/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Pre-slab inspection: South half of basement level, #4 rebar in place, plumbing has been wrapped. Ok to place concrete in progress areas. |
| 03/12/2026 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
3/12/26: Elevator shaft top out per approved plans ok to proceed with concrete placement |
| 09/25/2025 |
COT - HCBU - Masonry Pregrout |
|
Partial Pass |
Rebar for column (F7) at C/1.8, elevator pad at,B.T - A.5/1.5 -2. OK to place concrete in progress areas. |