Inspection Status: Partial Pass

Inspection History: COT - LCBU - Masonry Pregrout 

Permit Number - TC-COM-0824-01528

Inspection Description - COT - LCBU - Masonry Pregrout 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/05/2025 COT - LCBU - Masonry Pregrout  Partial Pass
06/10/2025 COT - LCBU - Masonry Pregrout  Partial Pass
06/11/2025 COT - LCBU - Masonry Pregrout  Partial Pass
06/12/2025 COT - LCBU - Masonry Pregrout  Partial Pass 1st lift. East wall approximately 90’. Shy 10’ away from north corner. Okay to grout progress areas. 6/12/2025
06/17/2025 COT - LCBU - Masonry Pregrout  Partial Pass
06/18/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-18-25: reinforcement on cmu wall located on south side verified per plans. Okay to grout-3rd lift at 12'.
06/20/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-20-25: top out on approximately 140' of south wall -16' 8".
06/23/2025 COT - LCBU - Masonry Pregrout  Partial Pass
06/25/2025 COT - LCBU - Masonry Pregrout  Partial Pass Second lift of site wall (Southwest) approximately 45 feet at gate entrance. Screen wall South and East at last lift and grout cap< approximately 125’. Ok to,grout progression areas.
06/26/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-26-25: top out at East cmu wall-15' 4"-okay to pour.
06/27/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-27-25: South entrance of west wall is okay to grout 3rd lift at 12'. Video inspection was conducted later in the afternoon for same area. Reinforcement was verified per plans for 4th lift at 16'-okay to grout which is set for 6-30-25 at 0530 hours. Reinforcement on remaining west wall verified and is okay to grout 2nd lift at 8
06/30/2025 COT - LCBU - Masonry Pregrout  Partial Pass 6-30-25: reinforcement on approximately 140' on north cmu wall verified per plans. Okay to grout 1st lift at 4'.
07/01/2025 COT - LCBU - Masonry Pregrout  Partial Pass East side of project West exterior wall at 8’ - 12’, approximately 224’. Ok ^o,grout progress areas.
07/03/2025 COT - LCBU - Masonry Pregrout  Partial Pass North screen wall (12” block) at second lift; approximately 200’ from Northeast corner to West. Ok to grout progress areas.
07/10/2025 COT - LCBU - Masonry Pregrout  Partial Pass
07/22/2025 COT - LCBU - Masonry Pregrout  Partial Pass
07/25/2025 COT - LCBU - Masonry Pregrout  Partial Pass 7/25/2025 partial pass, Second lift, west half of the north wall. Approximately 182'. Okay to grout progress areas.
07/28/2025 COT - LCBU - Masonry Pregrout  Partial Pass
07/29/2025 COT - LCBU - Masonry Pregrout  Partial Pass Third lift on North wall at West half of wall. Ok to .grout progress areas.
07/30/2025 COT - LCBU - Masonry Pregrout  Partial Pass
08/08/2025 COT - LCBU - Masonry Pregrout  Partial Pass