Parcel: 13313005E


Addresses:

1300 N PRUDENCE RD


Inspection Status: Requested

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0823-02110

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Requested

Date Description Inspector Results Comments
COT - LCBU - Excavation/Rebar/Zoning  Requested
02/15/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Retaining Wall footing.
02/20/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Balance of East side retaining wall footing.
02/26/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 12/7/23: reinforcing for two retention basin weir mats on west side of site OK to pour

Retaining Wall footing.

Balance of East side retaining wall footing.

2/26/24: New Retaining wall at north east corner at track per detail 103 passed. Ok to pour .
03/08/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Balance of retaining wall; pre-grout.
04/16/2024 COT - LCBU - Excavation/Rebar/Zoning  Canceled 4/16/24 - CA per Art
09/17/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass
09/20/2024 COT - LCBU - Excavation/Rebar/Zoning  Not Ready Met with representatives from Lloyd construction and from Desert Christian school to look over the area that they are anticipating wanting a TCO for this coming week. We walked this site and I pointed out things that were wrong and would need to be changed or completed correctly in this coming week if they wanted their TCO. Some of the sidewalk they’re planning on using east of the new football field is OK for you, but there is an area that is a driveway into the field that is noncompliant for cross slope at this time. I have advised the school and the contractor that this area will be upon them to choose whether they use it or not due to the noncompliance of sloping grade. Reinspection site will be scheduled for Monday so that we can look at what is being done in the parking lot that they want to use. Pavement will be placed this coming week and should be done and complete by next Friday the 27th. They also schedule another inspection on the 26th to verify that they have completed everything they need to for this event. I have reminded them that all areas were pedestrian. Traffic is adjacent to the particular traffic. Will have to have a 6 inch vertical separation.
09/26/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Ok to grout first4 ‘ lift
10/03/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass The site has been checked and is OK for a level four TCO for this weekend and next weekend.
10/18/2024 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Retaining Wall Footer (north east), 30 feet of wall on the east side of the Access road from the southern parking lot to the northern parking lot
12/07/2023 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 12/7/23: reinforcing for two retention basin weir mats on west side of site OK to pour