Inspection Status: Not Ready
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 05/22/2025 |
BULD - Electrical Clearance |
|
Not Ready |
1-Conduits requested are not our jurisdiction. 2-Conduits are incomplete. |
| 06/04/2025 |
BULD - Electrical Clearance |
|
Partial Pass |
Secondary service lines (3 each 3” conduits) from meter to transformer location. Ok to cover progress areas. |
| 07/30/2025 |
BULD - Electrical Clearance |
|
Passed |
ECO |
| 12/18/2024 |
BULD - Electrical Clearance |
|
Re-inspection required |
12-18-24, contractor scheduled electrical clearance for a temporary service but is not ready for inspection. Tucson Electric Company must first allow the service location in question to be activated. Once service is provided and the panel is mounted containing all the required equipment then the city will be able to inspect to provide temporary power. |
| 12/26/2024 |
BULD - Electrical Clearance |
|
Partial Pass |
Clearance for TEP TMPP. 12/26/2024 |