Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Masonry Pregrout
Permit Number - TC-COM-0823-02034
Inspection Description - COT - HCBU - Masonry Pregrout
Inspection Status - Partial Pass
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/02/2025 | COT - HCBU - Masonry Pregrout | Partial Pass | 1-2-25, stair towers complete. Elevator 1 is at top of 6th lift and #2 is at top of 7th lift. Okay to pour grout at progress areas. | |
12/05/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Both stair towers and elevator shafts. 1st lift reinforcements per plan. Okay to grout. 12/5/2024 | |
12/12/2024 | COT - HCBU - Masonry Pregrout | Re-inspection required | Provide field report from SI for second lift of stairs and East elevator; West elevator not ready. | |
12/13/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 12/13/24: Okay to grout 2nd lift of CMU walls for stairwells and elevators. | |
12/17/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 3 rd lift at stairs and elevators | |
12/20/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 4th lift at both stairs and Elevator Two. | |
12/23/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 12/23/2024. 5th lift at both stairs and elevator #2. 4th lift at elevator #1. Okay to grout progress areas. | |
12/24/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | Both stair towers and elevator shafts. 1st lift reinforcements per plan. Okay to grout. 12/5/2024 Provide field report from SI for second lift of stairs and East elevator; West elevator not ready. 12/13/24: Okay to grout 2nd lift of CMU walls for stairwells and elevators. 3 rd lift at stairs and elevators 4th lift at both stairs and Elevator Two. 12/23/2024. 5th lift at both stairs and elevator #2. 4th lift at elevator #1. Okay to grout progress areas. 12/24/24: 5th lift at north west elevator ok to grout progress areas. |
|
12/27/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 12/27/2024 6th lift at both Stair towers. NW&SE. okay to grout progress areas. | |
12/30/2024 | COT - HCBU - Masonry Pregrout | Partial Pass | 12/30/2024 6th lift at both elevator towers. NW&SE. okay to grout progress areas. |