Inspection Status: Partial Pass
Inspection History: COT - LCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/10/2024 |
COT - LCBU - Building Final |
|
Partial Pass |
1/10/24: work performed was not on building 1, building#8 unit#427 was the unit that was damaged. Revision will need to be made to address proper building and unit. Contractor also wants to add Reconnect to permit since TEP turned off power to unit. |
| 09/23/2024 |
COT - LCBU - Building Final |
|
Not Ready |
|
| 10/23/2024 |
COT - LCBU - Building Final |
|
Passed |
|