Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Underground 

Date Description Inspector Results Comments
03/12/2025 COT - LCEL - Electrical Underground  Partial Pass Trenching and conduits for scales as per photos. Ok to cover progress areas.
03/20/2025 COT - LCEL - Electrical Underground  Partial Pass Conduit from slab to scales area. Ok to cover conduit placement.
06/12/2025 COT - LCEL - Electrical Underground  Passed
08/16/2024 COT - LCEL - Electrical Underground  Partial Pass Starting point. X2 2" conduits for communication and cameras. X1 1 1/2" for power. Schedule 40 at 24" depth top of pipe. South entrance 80' from SES. Along fence line to pull box stubbed up into box. (260') (trench 3 ) IDF point to IDF. 8/16/2024
08/19/2024 COT - LCEL - Electrical Underground  Partial Pass 8/19/24 - sections 4 + 5 + 10' branch to video cab. Ok to backfill. All of required conduits, as described on 8/16/24, are in place.
08/22/2024 COT - LCEL - Electrical Underground  Partial Pass 8/22/24 - trench section 6 with 1 - 2" conduit ok to backfill.
09/03/2024 COT - LCEL - Electrical Underground  Partial Pass
09/06/2024 COT - LCEL - Electrical Underground  Partial Pass 9/6/24 - trench section 11 - wrapping the NW corner with 1 - 2" conduit. Stub up conduit connections are in place for Christy boxes,
light poles, and cameras, which will complete section 11. Ok to backfill.
09/10/2024 COT - LCEL - Electrical Underground  Partial Pass Partial for Trench 7 (east/west at the center of project), 1" conduit to Light-pole 5, 6, 7
09/12/2024 COT - LCEL - Electrical Underground  Partial Pass Partial for Trench 8 (north/south at the center of project), 2" and 1" conduit ending Christy boxes between Light-pole 5 and 3, okay to backfill progress areas
09/18/2024 COT - LCEL - Electrical Underground  Partial Pass Partial for 2", 1 1/2" and 1" conduit starting at Light pole 5 to Panel A in trench 2 (north/south at the center of project). Also 3- 2" conduit from trench 3 to Communications vault, okay to backfill progress areas