Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Interior Shear Bracing
Permit Number - TC-COM-0823-02017
Inspection Description - COT - HCBU - Interior Shear Bracing
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/10/2025 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level Three. | |
| 01/24/2025 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level Two | |
| 02/24/2025 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level One, Guest Rooms. | |
| 03/13/2025 | COT - HCBU - Interior Shear Bracing | Passed | drywall @ stairwells | |
| 04/10/2025 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 06/10/2024 | COT - HCBU - Interior Shear Bracing | Not Ready | ||
| 10/21/2024 | COT - HCBU - Interior Shear Bracing | Partial Pass | Hold-downs for Level Four gestrroms. | |
| 10/29/2024 | COT - HCBU - Interior Shear Bracing | Partial Pass | Looked at hold-down on Level Three. | |
| 11/01/2024 | COT - HCBU - Interior Shear Bracing | Partial Pass | Drywall at corridors. | |
| 11/18/2024 | COT - HCBU - Interior Shear Bracing | Passed | 11/18/24: All hold downs on levels 1 through 4 are properly installed and secured to studs with the required nails. Okay to proceed with other work. | |
| 12/04/2024 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level Four: Corridor walls, ceilings of guest rooms, and demising walls of guest rooms. Level Three: Corridors. |
|
| 12/04/2024 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level Four: Corridor walls, ceilings of guest rooms, and demising walls of guest rooms. Level Three: Corridors. |
|
| 12/06/2024 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level Four complete. |