Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - TC-COM-0823-01965
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/30/2024 | ENGR Engineering Final | Passed | OKAY FOR LEVEL 4 TCO AUTISM CENTER ISOLATED FROM ADJOINING CONSTRUCTION |
|
| 03/20/2024 | ENGR Engineering Final | Not Ready | Recall for Monday, Move Porta Jon to contractor area. Have tenant move storage boxes off of site. Cut branches up off of ground to be able to park a van under the tree. Clear branch from in front of of drive line parking sign. |
|
| 03/28/2024 | ENGR Engineering Final | Not Ready | Storage containers not yet moved and taking up 5 parking spaces Tree branches taking up 3 parking spaces. Branch blocking no parking sign needs to be removed. |
|
| 04/01/2024 | ENGR Engineering Final | Partial Pass | All items have been completed for a TCO4 for occupancy on the south side of the building only. Once this job has been fully completed we will be able to look at the entirety of the job for a final CO. Items that needed to be completed, 1) Temp. fencing to guard customers from the construction area. 2) Storage boxes moved to a non parking area. 3) Tree branches cut to increase the amount of available parking spaces 4) Port-a-Jon moved to a construction area. |
|
| 05/28/2024 | ENGR Engineering Final | Canceled | Will be ready for Monday the 3rd | |
| 06/03/2024 | ENGR Engineering Final | Passed | Everything looks good on the engineering side for a full CO |