Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - TC-COM-0724-01409
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/24/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Grid lines E1.4-E4. E4-E7. Columns A.1-B.1. B.1-G. Footings and reinforcement per plan. Okay for concrete placement in footings. 4/23/2025 | |
| 04/25/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 04/29/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 04/30/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 05/15/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 05/16/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 05/20/2025 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | ||
| 05/22/2025 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | ||
| 05/28/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 06/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 06/26/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6-26-25: reinforcement for footings on line N 4-7 verified per plans-okay to pour. | |
| 07/01/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Grid lines E1.4-E4. E4-E7. Columns A.1-B.1. B.1-G. Footings and reinforcement per plan. Okay for concrete placement in footings. 4/23/2025 4/25/25 16 spread footers for Colin bases OK to place concrete Footers C1 F1 4/29/25 footing from E to M on Grid E7 ok to place concrete. grid E6, J H G F FOOTINGS, Gridline E5, J H G F, E3, J H G F , E2 J H G F and E1 J - D ok to place concrete. 4/30/25 Grid E4 D TO L OK TO PLACE CONCRETE 5/15/25 footing at grid line M 77' heading west from E7 ok for concrete 5/16/25 footing from 77' point grid line M to loading dock to west ok for concrete 5/28/25 4th lift for entry vestibule ok to place grout 6/23/25 footings on line E2.4 FROM M TO N AND ON N E2.4 THROUGH 4 6-26-25: reinforcement for footings on line N 4-7 verified per plans-okay to pour. 7/1/25: continuous footing building/loading dock footings GL N/7-9.2, GL 9.2/L.4-N, GL L.4/9.2-9.9, GL 9.9/K-L.4 |
|
| 07/03/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 07/09/2025 | COT - HCBU - Excavation/Rebar/Zoning | Canceled | 7/9/2025 canceled per contractor. | |
| 07/10/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 07/18/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/09/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/10/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Total of 4 footers on grid line M. Okay for concrete placement. 9/10/2025 | |
| 09/11/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/16/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/18/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/25/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 09/30/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/02/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/06/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/07/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/09/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/17/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/20/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/21/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/22/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 10/30/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 11/24/2025 | COT - HCBU - Excavation/Rebar/Zoning | Not Ready | ||
| 12/03/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | ||
| 12/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass |