Parcel: 13415002A


Addresses:

7730 E BROADWAY BL


Inspection Status: Not Ready

Inspection History: COT - LCPL - Yard Water Line 

Permit Number - TC-COM-0724-01374

Inspection Description - COT - LCPL - Yard Water Line 

Inspection Status - Not Ready

Date Description Inspector Results Comments
07/31/2024 COT - LCPL - Yard Water Line  Not Ready work incomplete
07/31/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
08/01/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
08/05/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
08/09/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
08/14/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
08/16/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
8/16/24: Building 5 & 6 tie-ins made ok to backfill. Shading required
08/28/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
8/16/24: Building 5 & 6 tie-ins made ok to backfill. Shading required
8/28/24: building 5 laundry under air test passed ok to schedule tie-in inspection, building 7 air test passed ok to schedule tie-in inspection.
08/29/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
8/16/24: Building 5 & 6 tie-ins made ok to backfill. Shading required
8/28/24: building 5 laundry under air test passed ok to schedule tie-in inspection, building 7 air test passed ok to schedule tie-in inspection.
8/29/24: building 5 laundry tied in. Ok to backfill, building 7 tied-in. Ok to backfill, shading required
09/20/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
8/16/24: Building 5 & 6 tie-ins made ok to backfill. Shading required
8/28/24: building 5 laundry under air test passed ok to schedule tie-in inspection, building 7 air test passed ok to schedule tie-in inspection.
8/29/24: building 5 laundry tied in. Ok to backfill, building 7 tied-in. Ok to backfill, shading required
9/20/24: Building 3 lines per plan and under pressure. Ok to proceed with Tie-in.
09/24/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
8/16/24: Building 5 & 6 tie-ins made ok to backfill. Shading required
8/28/24: building 5 laundry under air test passed ok to schedule tie-in inspection, building 7 air test passed ok to schedule tie-in inspection.
8/29/24: building 5 laundry tied in. Ok to backfill, building 7 tied-in. Ok to backfill, shading required
9/20/24: Building 3 lines per plan and under pressure. Ok to proceed with Tie-in.
9/24/24: Building 3 lines have been tied in ok to backfill. Shading required.
10/02/2024 COT - LCPL - Yard Water Line  Partial Pass 7/31/24: building 9 Main water line per plan and under test at 70psi. ok to backfill. Shading required.
8/1/24: building 9 tied in ok to backfill, all joints were dry and connections were made with approved fittings.
8/5/24: building 10 main water line per plan and under pressure at 70psi. Ok to proceed .
8/9/24: building 10 main water tied in ok to backfill. Building 6 water line per plan and under 70psi ok to schedule tie-in inspection.
8/14/24: Building 5 lines per plan and under 70PSI ok to proceed with tie-in.
8/16/24: Building 5 & 6 tie-ins made ok to backfill. Shading required
8/28/24: building 5 laundry under air test passed ok to schedule tie-in inspection, building 7 air test passed ok to schedule tie-in inspection.
8/29/24: building 5 laundry tied in. Ok to backfill, building 7 tied-in. Ok to backfill, shading required
9/20/24: Building 3 lines per plan and under pressure. Ok to proceed with Tie-in.
9/24/24: Building 3 lines have been tied in ok to backfill. Shading required.
10/2/24: Building 2 lines per plan under pressure ok to proceed with Tie-in.
Building 4 Partial per plans under pressure ok to proceed with tie-in at progress area.