Parcel: 11709158B


Addresses:

401 E 22ND ST


Inspection Status: Partial Pass

Inspection History: COT - LCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-0724-01365

Inspection Description - COT - LCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
09/11/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Southwest parking lot; 5 each light pole caisson footings with electric ufers in place. Ok to place concrete in progress areas.
09/12/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass North parking lot, 5 light pole caisson footings with cages and electric conduits. Ok to place concrete in progress areas.
09/17/2025 COT - LCBU - Excavation/Rebar/Zoning  Not Ready
09/19/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Musco lights (9) at North and Northwest areas.
10/01/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Musco lights in place. B2 (ML1000A), A1 (ML1004A), B1 (ML1006A), S1 (ML1018A) okay for concrete placement. 10/1/2025
10/07/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 1. Pass for exterior lights, ok to pour progress areas.
10/09/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Light poles. Station (LP1034A2) (LP1046A) (LP1040A) (LP1042A1) (LP1038A2) (LP1036A) total of 6. Okay for concrete placement. 10/9/2025
10/13/2025 COT - LCBU - Excavation/Rebar/Zoning  Canceled
10/14/2025 COT - LCBU - Excavation/Rebar/Zoning  Re-inspection required 10-14-25: reschedule inspection when trench/caisson footings contain no water.
10/15/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass 10-15-25: excavation/reinforcement/ electrical underground on 5 light pole cages verified per plans-okay for concrete plate on station's-LP103OA1, LP1028A1,LP1026A,LP1062A2, LP1066A1.
10/28/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass
10/30/2025 COT - LCBU - Excavation/Rebar/Zoning  Partial Pass Partial to pour for 5 light poles LP106AI, LP1054A2, P1135AI, LP044A, LP102A28A2
11/03/2025 COT - LCBU - Excavation/Rebar/Zoning  Canceled Contractor cancelled; will reschedule for 4 November