Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/20/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Caisson footings for canopy columns: six columns for three canopies. Ok to place concrete in progress areas. |
| 01/29/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Partial pass. Footers approved for comfort building (bathroom building). Okay for concrete placement. Electrical conduit in place. 1/29/2026 |
| 02/18/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Site wall at new restroom at 0’ - 4’. Ok to grout progress area. |
| 03/11/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
|
| 09/11/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Southwest parking lot; 5 each light pole caisson footings with electric ufers in place. Ok to place concrete in progress areas. |
| 09/12/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
North parking lot, 5 light pole caisson footings with cages and electric conduits. Ok to place concrete in progress areas. |
| 09/17/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
|
| 09/19/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Musco lights (9) at North and Northwest areas. |
| 10/01/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Musco lights in place. B2 (ML1000A), A1 (ML1004A), B1 (ML1006A), S1 (ML1018A) okay for concrete placement. 10/1/2025 |
| 10/07/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1. Pass for exterior lights, ok to pour progress areas. |
| 10/09/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Light poles. Station (LP1034A2) (LP1046A) (LP1040A) (LP1042A1) (LP1038A2) (LP1036A) total of 6. Okay for concrete placement. 10/9/2025 |
| 10/13/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
|
| 10/14/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Re-inspection required |
10-14-25: reschedule inspection when trench/caisson footings contain no water. |
| 10/15/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
10-15-25: excavation/reinforcement/ electrical underground on 5 light pole cages verified per plans-okay for concrete plate on station's-LP103OA1, LP1028A1,LP1026A,LP1062A2, LP1066A1. |
| 10/28/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
|
| 10/30/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Partial to pour for 5 light poles LP106AI, LP1054A2, P1135AI, LP044A, LP102A28A2 |
| 11/03/2025 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
Contractor cancelled; will reschedule for 4 November |