Parcel: 11709158B


Addresses:

401 E 22ND ST


Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Underground 

Permit Number - TC-COM-0724-01365

Inspection Description - COT - LCEL - Electrical Underground 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
08/22/2025 COT - LCEL - Electrical Underground  Partial Pass Light pole (P4) Cristy box from (PB33) feeding P2, P3 and PBx2 1” schedule 40 at approximately 32”. Okay to backfill all progress areas. Shading required. 8/22/2025
09/03/2025 COT - LCEL - Electrical Underground  Partial Pass 9-3-25: verified trench depth on 1" Schedule 40 electrical conduits for 5 light pole cages located on northwest side of park. Okay to backfill progress areas with shading materials.
09/05/2025 COT - LCEL - Electrical Underground  Partial Pass Conduits (1”) for light poles at basketball courts. Ok to cover progress areas.
09/22/2025 COT - LCEL - Electrical Underground  Partial Pass X2 schedule 40. 2” for musco lighting. 1” is for parking lot lighting. 24” depth. Running East to west. From parking lot light pole (Lp1004A1)-(ML1020A) okay to backfill all progress areas. 9/22/2025
09/29/2025 COT - LCEL - Electrical Underground  Partial Pass X2 2”. 1 For lighting at MUSCO (B3) (M4016A1) - (A3) . X1 1 1/2” from switch gear running to transformer circuit #32 future. 9/29/2025
10/03/2025 COT - LCEL - Electrical Underground  Partial Pass 10-3-25: verified trench depth on Schedule 40 conduits for lighting Musco (A30) (MLIOMA)heading in a Southwest direction for future light pole & ramada just passed the sidewalk. Okay to backfill approximately 240' of open trench.
10/09/2025 COT - LCEL - Electrical Underground  Partial Pass X1 2” x1 1 1/2” x1 1” Ml1012A under ground running south to Cristy box for disconnect at pump house. 2” From pump house to musco light B4. 1” feeding column for Ramada at station Sc1004A. Okay to backfill progress areas. Shading is required. 10/9/2025
10/13/2025 COT - LCEL - Electrical Underground  Canceled
10/14/2025 COT - LCEL - Electrical Underground  Re-inspection required 10-14-25: reschedule inspection when trench/caisson footings contain no water.
10/15/2025 COT - LCEL - Electrical Underground  Partial Pass 10-15-25: excavation/reinforcement/ electrical underground on 5 light pole cages verified per plans-okay for concrete plate on station's-LP103OA1, LP1028A1,LP1026A,LP1062A2, LP1066A1.
10/16/2025 COT - LCEL - Electrical Underground  Partial Pass 1” schedule 40 @ 24” depth From Station LP1060A, LP1062A , LP1064A, LP1066A, LP1068A. (From 4th street hooking around towards 22nd heading East) at perimeter lighting. Okay to backfill progress areas. Shading required. 10/16/2025
10/23/2025 COT - LCEL - Electrical Underground  Partial Pass Electric conduits in place (2 @ 1 1/2” - 1 @ 2”) from basketball courts to East entry: approximately 450’. Ok to back fill progress area.
10/30/2025 COT - LCEL - Electrical Underground  Partial Pass Partial to pour for 5 light poles LP106AI, LP1054A2, P1135AI, LP044A, LP102A28A2
11/13/2025 COT - LCEL - Electrical Underground  Partial Pass Electric conduits for gear box and SES cabinet: conduits at 1” - 2 1/2” conduits. Ok to cover cabinet and box areas.
11/20/2025 COT - LCEL - Electrical Underground  Canceled Contractor cancelled due to weather.
11/21/2025 COT - LCEL - Electrical Underground  Partial Pass 11-21-25: verified 2 separate trenches with 3-Schedule 40 electrical conduits in each running from east to west in center of site. Electrical conduits range from 1 1/2" to 2" in size and are secondary conduits for parking lot lighting, scoreboard, and musco sport lighting. Okay to backfill approximately 400' of combined trenching using shading materials.
11/25/2025 COT - LCEL - Electrical Underground  Partial Pass Underground conduits (2” - 1”) at Light S1 to junction box Northeast; approximately 175’; trenching with conduits (2” - 1”) at Skate board area South and West; approximately 300’. Ok to cover progress areas.